Work gets underway to transform Roumelia Lane


Roumelia Lane in Boscombe is set for a facelift as work gets underway to improve the area.

Works have started in Roumelia Lane as part of the regeneration of Boscombe which will include, resurfacing of the road, the introduction of a new 20mph speed limit as well as a one way system.

Work will run for approximately 12 weeks with a series of phased road closures while work takes place. However, pedestrian access will be maintained throughout.


The Council allocated £196k for a package of works to enhance the area which also included better street lighting and CCTV was installed thanks to funding from the Crime and Disorder Reduction Partnership.